Question: i hope it gets solved asap , thank you a) clo Draw an activity-on-node diagram for the project outlined in the following table. Task Duration

i hope it gets solved asap , thank you a) clo
i hope it gets solved asap , thank you
a) clo Draw an activity-on-node diagram for the project outlined in the following table. Task Duration (Weeks) Follows 3 B 7 A 9 A D 3 E BD F 3 E G 2 F H 3 CF 1 5 G H 11 (15 marks) b) Identify the critical path in the project drawn in question 1a. What is the project duration? (3 marks) c) Discuss what would happen to the project if the estimate for TASK B was wrong and its duration had to be amended to 14 weeks. (7 marks) (Total: 25 marks)