Question: i keep getting this question wrong. i have already asked this question and got another wrong answer. please help Assume you are risk-averse and have
Assume you are risk-averse and have the following three choices. Expected Value Project A B C $ 2,440 2,560 2,020 Standard Deviation $ 1,420 1,960 910 a. Compute the coefficient of variation for each. Note: Round your answers to 3 decimal places. Answer is complete but not entirely correct. Project A B C Coefficient of Variation 58.197 76.562 X 45.049 x