Question: I need a quick answer, please. 19. Assume you have another project with the following information : Activity A (Duration = 1, Predecessor = None),

I need a quick answer, please.
19. Assume you have another project with the following information : Activity A (Duration = 1, Predecessor = None), Activity B (Duration 2, Predecessor = A), Activity C (Duration = 4, Predecessor = B), Activity D (Duration =3, Predecessor = C, E, G), Activity E (Duration = 1, Predecessor = A), Activity G (Duration 1, Predecessor = A), A feeding buffer can be inserted between * (2 Points) A and B A and G A and E E and D None of the others