Question: i need answer with full solution Question 1-) What is the CPI and SPI of the project respectively? A-) CPI=0.9 and SPI=1.2 B-) CPI=1.2 and
Question 1-) What is the CPI and SPI of the project respectively? A-) CPI=0.9 and SPI=1.2 B-) CPI=1.2 and SPI=0.9 C-) CPI=0.75 and SPI=1.1 D-) CPI=1.1 and SPI=0.75 Question 2-) What is the CV and SV of the project respectively? A-) CV=-$150,000 and SV=100 man/days B-) CV= $150,000 and SV=-100 man/days C-) CV=-$100,000 and SV=-100 man/days D-)CV=$100,000 and SV=100 man/days