Question: I need explanation of the float activity below Activity description Activity ID A B D E F G H Immediate Predecessor None B B Collect

I need explanation of the float activity below
Activity description Activity ID A B D E F G H Immediate Predecessor None B B Collect requirements Analyze processes Analyze data Design processes Design data Design screens Design reports Program Test and document Install Duration In weeks 2 3 3 7 6 1 5 4 8 2 C D DE F,G G HI J A) O A 2 2 B 5 5c 8 17 3 20 0 2 2 2 3 5 5 E 11 5 D 12 12 F 13 6 09 6 12 5 7 12 20 1 21 12 G 17 17 H 21 12 5 17 21 4 25 17 1 25 25 J 27 17 8 25 End 27 25 2 27