Question: I need help creating a status report using the following data Earned Value Period Estimate at completion (EAC) Actual Cost (AC) (% actual work completed)

I need help creating a status report using the following data

Earned Value Period Estimate at completion (EAC) Actual Cost (AC) (% actualwork completed) *BAC 153.94 175.3 Planned Value (% planned work completed) *BAC

Earned Value Period Estimate at completion (EAC) Actual Cost (AC) (% actual work completed) *BAC 153.94 175.3 Planned Value (% planned work completed) *BAC 110 Variance at completion (VAC) Schedule Performace Index (SPI) EV/pv 1.13 1.11 0.97 Performance Index(CPl) EV/AC 1.31 131 Percent Complete Index Budget(PCl-8) EV/BAC 0.24 0.59 0.75

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!