Question: I need help creating a status report using the following data Earned Value Period Estimate at completion (EAC) Actual Cost (AC) (% actual work completed)
I need help creating a status report using the following data


Earned Value Period Estimate at completion (EAC) Actual Cost (AC) (% actual work completed) *BAC 153.94 175.3 Planned Value (% planned work completed) *BAC 110 Variance at completion (VAC) Schedule Performace Index (SPI) EV/pv 1.13 1.11 0.97 Performance Index(CPl) EV/AC 1.31 131 Percent Complete Index Budget(PCl-8) EV/BAC 0.24 0.59 0.75
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
