Question: I need help solving this problem For the set of tasks given below, do the following: Click here for the Excel Data File a. Determine

I need help solving this problem
I need help solving this problem For the set of tasks given
below, do the following: Click here for the Excel Data File a.

For the set of tasks given below, do the following: Click here for the Excel Data File a. Determine the minimum cycle time and then calculate the cycle time for a desired output of 500 units in a seven-hour day. (Round your answers to 1 decimal place.) b. Determine the minimum number of workstations for output of 500 units per day. (Round up your answer to the next whole number.) c. Balance the line using the greatest positional weight heuristic. Break ties with the most following tasks heuristic. Use a cycle time of 50 seconds. d. Calculate the percentage idle time for the line using the 50 second cycle time. (Round your answer to 1 decimal place.)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!