Question: I need help Solving this question. Q3: Considering the following project activities: Duration (weeks) 4 Activity B D E F G H 5 7 3
I need help Solving this question.
Q3: Considering the following project activities: Duration (weeks) 4 Activity B D E F G H 5 7 3 6 6 Predecessors None None B AC B D D E,G 8 4 1. Draw the project network diagram 2. Identify all the paths through the network and their lengths 3. Which activity or activities have the most slack? 4. Management has determined that the project must complete in 25 weeks or less and that "cost is no object". How many paths will need to be crashed in order to meet this goal? Which activities do not need to be considered for crashing