Question: I need help to answer A / B / C / D , I hope the solution is computer-based, not handwritten, as I cannot read

I need help to answer A / B / C / D , I hope the solution is computer-based, not handwritten, as I cannot read handwriting well

I need help to answer A / B / C / D , I hope the

TIME-COST TRADEOFF EXERCISE B N=5, $40,000 C = 5, $40,000 N=7, $50,000 C = 5, $56,000 Start Finish C D N=7, $30,000 N=7, $65,000 C = 6, $35,000 C=5, $69,000 * Times shown in weeks Based on the figure shown above, answer the following questions: a. What is the total cost and duration of the project if all activities are performed in their normal time? b. What is the per-week crash cost for: (1) Activity A? (2) Activity B? (3) Activity C? (4) Activity D? c. What is the shortest possible project completion time? d. What is the lowest possible cost to achieve the time given in answer c? (Provide the new total cost and the cost and durations used for each activity to achieve this cost and schedule.) Activity A: New cost: New duration: Activity B: New cost: New duration: . Activity C: New cost: New duration: Activity D: New cost: New duration: . New total cost

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!