Question: I need help with part 1- 3. If possible please include all steps. Thank you. Consider the following table: ACTIVITY PREC. ACT. TIME ESTIMATES (days)

I need help with part 1- 3. If possible please include all steps. Thank you.
Consider the following table: ACTIVITY PREC. ACT. TIME ESTIMATES (days) tml top 6 6 6 B A 4 5 6 A 2 4 6 D B 4 6 8 E 3 5 1 1 F D 5 5 3 1) Construct a PERT network. [NOTE: This is the most crucial part of the exercise. Make sure you have the correct network before proceeding to the next sections.] 2) By using ES, EF, LF, LS, find the slack of each activity and the critical path. 3) Find the completion time and the standard deviation () for the project, round off the standard deviation to the nearest hundredth: two decimal places. 4) What is the completion time at 95% confidence level? 5) What is the likelihood of this project being completed earlier than 19 days? 6) Between 13 and 15 daysStep by Step Solution