Question: PART I: PERT Consider the following table: ACTIVITY PREC. ACT. TIME ESTIMATES (days) to tml tp te A --- 2 3 4 B A 2

PART I: PERT

Consider the following table:

ACTIVITY PREC. ACT. TIME ESTIMATES (days)

to tml tp te

A --- 2 3 4

B A 2 4 6

C A 4 6 8

D A 4 5 6

E B 6 7 8

F D 1 3 5

G E, C, F 3 5 7

1. Construct a PERT network. (20 points)

[NOTE: This is the most crucial part of the exercise. Make sure you have the correct network before proceeding to the next sections.]

2. By using ES, EF, LF, LS, find the slack of each activity and clearly state the critical path. (10 points)

3. Find the completion time ( ) and the standard deviation () for the project round off the standard deviation to the nearest hundredth: two decimal places. (20 points)

[NOTE: Sigma is only computed on the critical path.]

4. What is the completion time at 68% and 95% confidence levels? (20 points)

5. What is the likelihood of this project being completed in more than 20 days? (15 points)

6. Between 16 and 18 days? (15 points)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!