Question: I need help with this and double checking my work Complete the MRP records, using the following information: - Production plans for complete kits are


I need help with this and double checking my work
Complete the MRP records, using the following information: - Production plans for complete kits are as follows: Start assembling 16,000 kits in week 2 Start assembling 9,500 kits in weeks 3,4 , and 5 Start assembling 15,000 kits in week 6 - The gross requirements for the system unit have already been given to you. For the remaining items, you will need to figure out the gross requirements. - All scheduled receipts, lead times, and beginning inventory levels are shown. Click the icon to view the MRP records. Construct the material requirements plan for item System unit (enter your responses as whole numbers). More Info