Question: I need help with this question please. Also, please include Excel formulas. table [ [ , Park Project Gantt Chart ] , [ Activity ,
I need help with this question please. Also, please include Excel formulas.
tablePark Project Gantt ChartActivityActivity Detail,PredecessorsANeed Assessment,BArchitect Assessment,ACSecure Funding,ADVoter Approval,CEContractor Selection,CFGround Preparation,B D EGDrainageIrrigationFHConstruction,G
More
questions
below
Question a Draw the Gantt Chart for the project in the above grid. Then list all the dependent paths for this project below.
Use Upper Case Letters To Represent Activities example A B C D E F
tablenote it not necessary that you have foPathPathPathPath
Question b What is the expected time to finish the project in weeks? Answer below in cell E
Weeks
Question c The city agreed to complete the Voter Approval Activity D in two weeks rather than three weeks. How long will it take to finish the project based on the new agreement? Answer below in cell E Weeks
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock