Question: I need it as soon as possible predecessor Activity A B D E F G H I J duration 5 20 4 2 10 8

I need it as soon as possible
predecessor Activity A B D E F G H I J duration 5 20 4 2 10 8 4 2 6 2 A B,C B,C B,C GH DE Given the above activates solve the following: 1. Constructing or prepare the above network diagram using Gantt Chart Techniques and CPM. 2. Fine out the total completion minimum completion time of the project. 3. Calculate the critical and non-critical path of both network diagram Gantt chart and CPM diagram. 4. What do you conclude from both above 1 and 2 , Explain your answersStep by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
