Question: i need part B also ! please 1 The following table lists the components needed to assemble an end item, lead times, and quantities on

i need part B also ! please
i need part B also ! please 1 The following table lists

1 The following table lists the components needed to assemble an end item, lead times, and quantities on hand. ts Item LT (week) Amount on hand End 3 0 -00 B 1 12 UNN C. 2 D 2 27 E 2 13 F 3 31 ONN G 2 7 OWL H 3 eBook Click here for the Excel Data File Hint Pint End Hom eferences B121 C DO) E21 FON G03 H14 E o. If 22 units of the end item are to be assembled, how many additional units of E are needed? (Hint You don't need to develop an MRP plan to determine this) Additional unit