Question: I need the answer as soon as possible QA: The network diagram of one of the projects and its data as in Table No (4),
I need the answer as soon as possible 
QA: The network diagram of one of the projects and its data as in Table No (4), so if I want to reduce the duration of the project by one day, find what I can do - 1- The cost of the project before the reduction 2- The activity or activities that will reduce its churation 3 Project sent after downwing th Question data 4 Cost(millions of dinars) duration (day) bent natural urgent natural 10 7 5 8 16 8 6 10 11 8 7 10 14 14 1 1 11 8 3 4 8 7 13 14 19 7 8 12 20 19 7 8 10 7 2 3 16 16 2 2