Question: I need the answer please can't find it -5 (Video) Actual materials price $220 per ton 6 (Video) Standard labor rate $13.50 per hour -7
I need the answer please can't find it

-5 (Video) Actual materials price $220 per ton 6 (Video) Standard labor rate $13.50 per hour -7 (Video) Standard materials price $222 per ton 8 a 11 (Video) Quantities 2A (Part ission) Actual hours incurred and used 4,100 hours Actual quantity of materials purchased and used 1,600 tons Standard hours used 4,180 hours s by Study Standard quantity of materials used 1,580 tons (a) Compute the total, price, and quantity variances for materials and labor. Total materials variance Materials price variance Materials quantity variance Total labor variance Labor price variance Labor quantity variance
Step by Step Solution
There are 3 Steps involved in it