Question: I need the LEVEL aggregate plan over the coming year. 4. Osprey Machine Works has the following demand requirements and other data for the upcoming

I need the LEVEL aggregate plan over the coming

I need the LEVEL aggregate plan over the coming year.

4. Osprey Machine Works has the following demand requirements and other data for the upcoming four quarters. Quarter Demand Previous quarter's output 2500 units 2300 Beginning inventory 200 units 2 2400 Stockout (backorder) cost $50 per unit 3 2600 Inventory holding cost $10 per unit at end of quarter 2100 Hiring workers $4 per unit Laying off workers $8 per unit What is the total cost of pursuing a level aggregate plan over the coming year? 4