Question: I NEED THE SOLUTION. 4.6 Complete the following table. Lead time for the part is two weeks. The lot size is 100. What is the

I NEED THE SOLUTION.
4.6 Complete the following table. Lead time for the part is two weeks. The lot size is 100. What is the projected available at the end of week 3? When is it planned to release an order? Week Gross Requirements Scheduled Receipts Projected Available 40 Net Requirements Planned Order Receipt Planned Order Release 1 20 2 65 100 3 35 Answer. Projected available at the end of week 3 is 20. An order release is planned for the beginning of week 2. 4 25Step by Step Solution