Question: I need to create and discuss a Work Breakdown Structure (WBS). summary of the project : The ASP construction company has an opportunity to take

I need to create and discuss a Work Breakdown Structure (WBS).

summary of the project :

The ASP construction company has an opportunity to take on a project to build a horse barn located in Los Altos Hills, CA. A traditionally constructed wooden barn is requested by the client due to the weather condition of the location, with the project budget set as $135,000. The client owns a community barn called the Dream Horse Barn and requires a new ten-stall barn as a new addition to the 15 acres of land since the facility is a breeding, training, and horse-riding center.

project tasks :

Task Name
Pre-Planning - Research and Design
Research building codes, zoning regulations, restrictions, and permits
Barn layout
Barn ventilation
Permitting
Apply for building codes
Apply for zoning regulations
Apply for any needed permits
Acquire Materials
Foundation materials
Barn exterior materials
Roof materials
Additional materials for storage
Site Preparation
Remove organic materials
Check site for proper drainage, water availability and electricity
Build Foundation
Use fill materials to build a high level foundation
Finish top layer with desired barn flooring
Install Supporting Structures
Install Trusses
Install roof support beams
Install roof, doors, and windows
Build Additional Features

project scope :

High-level project scope

  • A build of 10 stall barn, 3,600 Square foot
  • Materials to use are woods and metal
  • Budget cost not to exceed $135,000
  • Timeline not to exceed five-months
  • Materials to be purchased by the project team and project work is to be completed by our team, no outsourcing

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!