Question: I need to develop a network for this project 9.19 University Medical Center Relocation Project Information Activity Description Immediate Activity Predecessor(s) Time (weeks) A Meet
I need to develop a network for this project

9.19 University Medical Center Relocation Project Information Activity Description Immediate Activity Predecessor(s) Time (weeks) A Meet with department heads None B Appoint move advisory committee None C Plan public relations activities None D Meet with police department None N N O N B UN W E Meet with city traffic engineers A F Develop preliminary move plan A G Develop final move plan EFN H Establish move admissions policies B