Question: I only need the answer for d . please Schedule the following activities using CPM: b . What is the critical path? A - B

I only need the answer for d. please
Schedule the following activities using CPM:
b. What is the critical path?
A-B-D-F-G-H
A-B-D-E-H
A-C-E-F-G-H
A-C-E-H
c. How many weeks will it take to complete the project?
d. Which activities have slack, and how much?
B,2 weeks; D,1 week; E,4 weeks.
A.4 weeks; B,1 week; D,2 weeks.
C.2 weeks; F,2 weeks; G,2 weeks.
 I only need the answer for d. please Schedule the following