Question: I. Process Flow Diagram for Making a Shirt Consider the following process flow diagram for making a shirt. All steps (A, B, C, D, and

I. Process Flow Diagram for Making a Shirt Consider the following process flow diagram for making a shirt. All steps (A, B, C, D, and E) are necessary to create each finished unit (shirt). Each step employs a single worker. Exact task times, in minutes/unit, are shown at each step. For example, it takes exactly 4 minutes to stitch the front and back of the shirt. 4. Refer to the Process Flow Diagram for Making a Shirt. Assume that the process operates eight hours a day. What is its daily capacity, in units per day? 5. Refer to the Process Flow Diagram for Making a Shirt. Assume that the entire process is nunaing at bottleseck pacing. Coasider only the task of preparing the front, task A, in isolation from the reat of the process. What is the approximate labor utiluation at task A