Question: i put 9.2 but that's not the answer can u help me with a correct answer A project has the following activities with specified precedents
i put 9.2 but that's not the answer can u help me with a correct answer
A project has the following activities with specified precedents and expected durations (in hours). How much slack does Activity E have? Activity PrecedentDuration A 6.0 A 7.2 4.9 D BC 6.0 E BC 4.5 F D D 7.7 G E, F 3.9 Answer: 9.2