Question: I the following table the activities with their precedence sequence and expected time ( days ) are isted for a project: table [ [

I the following table the activities with their precedence sequence and expected time (days) are isted for a project:
\table[[Activity,Immediate Predecessor(s),Time (days)],[A,-,5],[B,A,2],[C,A,4],[D,B,5],[E,B,5],[F,C,5],[G,E, F,2],[H,D,3],[I,G, H,6]]
The correct AOA precedence diagram is shown in