Question: In the following table the activities with their precedence sequence and expected time (days) are listed for a project: Immediate Predecessor(s) Activity A A A


In the following table the activities with their precedence sequence and expected time (days) are listed for a project: Immediate Predecessor(s) Activity A A A - IOT MUO Time (days) 6 2 4 5 5 5 2 3 5 B C E, F D G H a) The activities on the critical path are b) The project length is days. Activity A Immediate Predecessor(s) Time (days) 1 B C D 0 0 0 D D 2 M ) H u w Nu u U E F G C E, F D H T G H Done