Question: ( i ) Use the information in the table above to draw a precedence network ( PERT ) . Each activity node should contain: Activity

(i) Use the information in the table above to draw a precedence network (PERT). Each activity node should contain: Activity label, Duration, Earliest start (ES), Earliest finish (EF), Latest start (LS),Latest finish (LF) and Float (use the British Standard BS 4335
labelling convention).
Show all calculations. Justify your estimates for activities B, H and K.
(ii) Identify the critical path of the activity network you created in part (i) above. Based on the given estimates, what is the minimum time required to complete the above project?
(iii) Explain in detail, 5 different measures a project manager could take to reduce the duration of the above project and discuss their overall impact on the project.
 (i) Use the information in the table above to draw a

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!