Question: I want real ans with solution if you gve wrong ans i will downvote Now you are being hired as a scheduler in the manufacturing

I want real ans with solution if you gve wrong ans i will downvote
Now you are being hired as a scheduler in the manufacturing unit of surgical instruments. Your job is to schedule four jobs on the two machines. The job processing time in minutes for the four jobs is given below: A D Machine 1 Machine 2 3.43 0.11 B 1.58 0.46 3.62 2.29 4.05 4.52 The optimal schedule using Johnson method and makespan for the jobs is: (A)BCBA, 12.79 minutes (B) ABCD, 5.41 minutes (C) DCBA, 12.79 minutes (D) CDBA, 5.41 minutesStep by Step Solution