Question: I will give thumbs up Problem 1- Apply Rate Monotonic (RM) task scheduling on the following period task sets: T1(4,1),T2(5,1),T3(10,1)Ti(p,c):p is the period and c

I will give thumbs up
Problem 1- Apply Rate Monotonic (RM) task scheduling on the following period task sets: T1(4,1),T2(5,1),T3(10,1)Ti(p,c):p is the period and c is the execution time. a) Argue about the schedulability of RM on this task set. b) Task 3 needs to increase its throughput (and hence, lower period). What would be the minimum period for T3 such that the 3 task sets are guaranteed to be RM schedulable