Question: _IC_ 2. In a PERT network, the earliest {activity} start time is the A} earliest time that an activity can he nished without delaying the

_IC_ 2. In a PERT network, the earliest {activity} start time is the A} earliest time that an activity can he nished without delaying the entire project. B} latest time that an activity can he started without delaying the entire project. C] earliest time that an activity can start without violation of precedence requirements. D} latest time that an activity can he nished without delaying the entire project. E} None of the above