Question: In a PERT network, the earliest ( activity ) start time is the Select one: latest time that an activity can be started without delaying
In a PERT network, the earliest activity start time is the
Select one:
latest time that an activity can be started without delaying the entire project.
earliest time that an activity can start without violation of precedence requirements.
earliest time that an activity can be finished without delaying the entire project.
latest time that an activity can be finished without delaying the entire project.