Question: ID (A) Description (Pour Foundation) Predecessor (None) Time (3) ID (B) Description (erect frame) Predecessor (A) Time (4) ID (C) Description (roof) Predecessor (B) Time

ID (A) Description (Pour Foundation) Predecessor (None) Time (3)

ID (B) Description (erect frame) Predecessor (A) Time (4)

ID (C) Description (roof) Predecessor (B) Time (4)

ID (D) Description (windows) Predecessor (B) Time (1)

ID (E) Description (doors) Predecessor (B) Time (1)

ID (F) Description (Electrical) Predecessor (B) Time (3)

ID (G) Description (Rough-in frame) Predecessor (C, D, E, F) Time (2)

ID (H) Description (Door opener) Predecessor (E, F) Time (1)

ID (I) Description (paint) Predecessor (G, H) Time (2)

ID (J) Description (cleanup) Predecessor (I) Time (1)

using AON Diagrams answer the following questions

Calculate the early and late activity times

a) Calculate the critical paths and times in all cases

b) If it asks about slack times, just answer for individual activity slack times.

There is no need to distinguish between free and total slack. You will receive a $500 bonus for completing the project within 15 working days.

The contract also contains a penalty clause in which you will lose $100 for each day the project takes longer than 15 working days.

Complete the forward and back pass. Do you expect to receive a bonus or a penalty on this project?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!