Question: identify critical path Identify the critical path Activity Immediate Predecessor (s) B C D E F G H none A B B, C D D
Identify the critical path Activity Immediate Predecessor (s) B C D E F G H none A B B, C D D E G H F, 1 Optimistic Most Likely Pessimistic Time Estimate Time Estimates Time Estimates (weeks) (weeks) (weeks) 2 3 6 2 4 5 6 7 10 3 5 7 4 7 11 2 5 8 4 5 7 5 6 9 4 8 11 3 3 3 3 14 15