Question: The table below lists 14 activities involved in a project by a consulting company hired to audit and evaluate of a manufacturer's logistics operations.


The table below lists 14 activities involved in a project by a consulting company hired to audit and evaluate of a manufacturer's logistics operations. The critical path is ACEHUL Activity predecessor (a) (m) A None B C D E F G H 1 Time (days) Most Immediate Optimistic likely Pessimistic (b) J K L M N None A A B. C D D E.F G, H 1 1 K LM 4.0 6.0 7.0 1.0 2.0 3.0 6.0 6.0 6.0 5.0 8.0 1.0 1.0 9.0 18.0 2.0 3.0 6.0 7.0 8.0 4.0 6.0 8.0 7.0 11.0 6.0 3.0 10.0 1.0 4.0 1.0 2.0 8.0 2.0 1.0 6.0 6.0 5.0 9.0 4.0 2.0 8.0 What are the expected times for Activity E and Activity K?
Step by Step Solution
There are 3 Steps involved in it
To calculate the expected time for an activity in a projec... View full answer