Question: Identify possible paths of this project.Find out only possible paths by constructing network diagram using AON notation. Do not Identify critical path Activity Immediate Predecessor

  1. Identify possible paths of this project.Find out only possible paths by constructing network diagram using AON notation. Do not Identify critical path

Activity

Immediate Predecessor (s)

Optimistic Time (weeks)

Most Likely (weeks)

Pessimistic Time (weeks)

A

-

2

3

5

B

A

2

4

5

C

A

5

7

8

D

B

3

5

7

E

B, C

4

7

11

F

D

2

5

8

G

D

4

5

7

H

E

5

6

8

I

G, H

4

8

10

J

F, I

2

3

3

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!