Question: Identify the critical path. How many days will the project take? ID Description Predecessor Time A Survey Site None 2 days B Excavate Site A
Identify the critical path.
How many days will the project take?
ID Description Predecessor Time
A Survey Site None days
B Excavate Site A days
C Install Power Lines B days
D Install Drainage B days
E Pour Foundation C D days