Question: Identify the critical path. ID Activity Predecessor Time A Order Review None 2 B Order standard parts A 3 C Produce standard parts A 1

Identify the critical path.
ID Activity Predecessor Time
A Order Review None 2
B Order standard parts A 3
C Produce standard parts A 10
D Design custom parts A 13
E Software Development A 18
F Manufacture custom hardware C, D 15
G Assemble B, F 10
H Test E, G 5
Group of answer choices
A, D, F, G, H
A, B, G, H
A, E, H
A, C, F, G, H