Question: Identify the Critical Path using CPM for this project. Use a table to list each activity slack. Activity Slack On Critical Path A 1 B

Identify the Critical Path using CPM for this project. Use a table to list each activity slack.
Activity Slack On Critical Path
A 1
B 0 Y
C 5
D 0 Y
E 6
F 5
G 0 Y
H 0 Y
Critical Path: B ->D-> G-> H