Question: IEN 514 Project Management Sem. 1, 21-22 a) Construct a bar chart (Gantt chart) for the activities shown in the table below and find the

IEN 514 Project Management Sem. 1, 21-22 a) Construct a bar chart (Gantt chart) for the activities shown in the table below and find the duration of the project, is this duration critical? Why or why not? ( 5 marks) Activity Description Immediate Time(week) Starting Finishing week predecessors week A Select site office 3 0 3 B Create a plan 0 5 C Determine B 3 5 8 personnel requirements D Design facility A,C 4 8 12 Construct interior D 8 12 20 F Select personnel C IN 8 10 G Hire new 10 14 employees H Move key F 2 10 12 personnel Financial B 5 5 10 arrangement Train personnel H, E, G 3 20 23