Question: If a channel on a 4 - year construction project was sized to carry the peak runoff rate of a storm with a 5 %

If a channel on a 4-year construction project was sized to carry the peak runoff rate of a storm with a 5% probability of occurring, what would be the chance (risk of failure) that a runoff event would occur during the 4 year project which would have a peak rate larger than this designed storm?