Question: If a construction activity on a project is on the critical path of the construction schedule for the project and the activity is delayed 1

If a construction activity on a project is on the critical path of the construction schedule for the project and the activity is delayed 1 day, then how many days of delay will there be to the finish date of the project?

a)- 1 day

b)0 days

c)+ 1 day

d)None of the above

Please with explanation