Question: If a customer order is placed on May 4, the company expects to begin processing it on May 10, and the order is shipped

If a customer order is placed on May 4, the company expectsto begin processing it on May 10, and the order is shippedon May 16, the manufacturing cycle time is then how many days

If a customer order is placed on May 4, the company expects to begin processing it on May 10, and the order is shipped on May 16, the manufacturing cycle time is then how many days long? Cycle time days If Toyota Motor Company receives an order on May 5, begins production on May 24, and ships the order on May 29 immediately following production, then what is the manufacturing cycle efficiency (MCE) ratio? (Enter your answer as a whole number.) Manufacturing cycle efficiency (MCE) ratio % If customer demand is 203,000 units per month, and available manufacturing capacity is 4,000 hours per week, what is the Takt time for this firm? (Round your answer to 2 decimal places.) Takt time hour/unit

Step by Step Solution

3.35 Rating (158 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

The manufacturing cycle time is the time taken from the start of production to the shipment of the product In this case Manufacturing cycle time Proce... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!