Question: If a firm accepts Project A it will not be feasible to also accept Project B because both projects would require the simultaneous and exclusive

If a firm accepts Project A it will not be feasible to also accept Project B because both projects would require the simultaneous and exclusive use of the same piece of machinery. These projects are considered to be:
Question 1 options:
economically scaled
operationally distinct
mutually exclusive
interdependent
independent