Question: If a project has 5 different phases which cost the following amounts. If contingency reserve is 10% and management reserve is 5%, what is the

If a project has 5 different phases which cost the following amounts. If contingency reserve is 10% and management reserve is 5%, what is the cost budget for the project?

If a project has 5 different phases which cost

$27,000

$29,700

$31.050

$31,185

Phase 1 Phase II Phase III Phase IV Phase V $3,000 $4,000 $10,000 $6,000 $4,000