Question: If a project is halfway completed, its schedule performance index is 1 1 0 percent, and its cost performance index is 9 5 percent, how

If a project is halfway completed, its schedule performance index is 110 percent, and its cost performance index is 95 percent, how is it progressing?
It is ahed of schedule and under budget.
It is ahead of schedule and over budget.
It is behind schedule and under budget.
It is behind schedule and over budget.
 If a project is halfway completed, its schedule performance index is