Question: If a project is halfway completed, its schedule performance index is 1 1 0 percent, and its cost performance index is 9 5 percent, how
If a project is halfway completed, its schedule performance index is percent, and its cost performance index is percent, how is it progressing?
It is ahed of schedule and under budget.
It is ahead of schedule and over budget.
It is behind schedule and under budget.
It is behind schedule and over budget.