4. In the context of earned value management (EVM): a) Given the total budget at completion...
Fantastic news! We've Found the answer you've been seeking!
Question:
Transcribed Image Text:
4. In the context of earned value management (EVM): a) Given the total budget at completion of a project is RM100 000, and the estimate at completion is RM120 000. Determine whether the project will cost more or less. (1 mark) b) Given the actual cost for a WBS item is RM1500 and its earned value is RM2000. Calculate the cost variance. (2 marks) c) If a project is halfway completed, its schedule performance index is 110 percent, and its cost performance index is 95 percent. Appraise the project performance in terms of whether it meets cost and time goals. (2 marks) (CLO1: PLO1: C4) 4. In the context of earned value management (EVM): a) Given the total budget at completion of a project is RM100 000, and the estimate at completion is RM120 000. Determine whether the project will cost more or less. (1 mark) b) Given the actual cost for a WBS item is RM1500 and its earned value is RM2000. Calculate the cost variance. (2 marks) c) If a project is halfway completed, its schedule performance index is 110 percent, and its cost performance index is 95 percent. Appraise the project performance in terms of whether it meets cost and time goals. (2 marks) (CLO1: PLO1: C4)
Expert Answer:
Answer rating: 100% (QA)
a The project will cost more since the estimate at completion EAC is higher than the total ... View the full answer
Related Book For
Posted Date:
Students also viewed these general management questions
-
Planning is one of the most important management functions in any business. A front office managers first step in planning should involve determine the departments goals. Planning also includes...
-
The graph of g consists of two straight lines and a semicircle. Use it to evaluate each integral. (a) g(x) dr (b) g(x) dr (c) () di y=g(x)
-
Many supermarkets provide regular shoppers with "loyalty cards" that the shoppers swipe each time they check out. By swiping the card, a shopper receives reduced prices on a few goods, and the...
-
Rewrite the attribute grammar of Figure 4.14 in the form of an ad hoc tree traversal consisting of mutually recursive subroutines in your favorite programming language. Keep the symbol table in a...
-
After returning from a skiing vacation in Vermont, Leslie Adel came down with Legionnaires Disease. He claimed it was from the water drunk at the ski resort and provided by Greensprings of Vermont...
-
The contribution format income statement for Huerra Company for last year is given below: The company had average operating assets of $2,000,000 during the year. Required: 1. Compute the companys...
-
3. a) Derive D = 4x using solid state diffusion theory b) Calculate the binary O2/N2 gas diffusivity at T = 300K and compare it to the pure 02 self- diffusivity. The molecular diameter of N2 is...
-
During 2021, Brewster Company earned revenues of $146 million. Brewster incurred, during that same year, salary expense of $28 million, rent expense of $23 million, and utilities expense of $19...
-
Julio is trying to figure out how many cannoli they needs to sell to make a target profit of $5,000 per month. They sells the cannoli for $5 each, with $2 in variable costs per unit. They also have...
-
Assume the bus clock is operating at 10 MHz. The SysTick initialization executes these instructions. void SysTick_Init (unsigned long period) { = 0; NVIC_ST_CTRL_R = NVIC_ST_RELOAD_R = xxx; //...
-
Project L costs $3,230, its expected cash inflows are $711 per year for 10 years, and its cost of capital is 12%. The project's (regular, i.e. "traditional") payback period is years. Round your...
-
4. (20 marks). Assume there is no tax and the book to market ratio equals 1. Current capital structure Debt: zero. Equity: $200,000, total number of shares: 5,000. EBIT: Normal - $21,000; Expansion...
-
Discuss the sophisticated strategies employed by modern operating systems for process synchronization and deadlock avoidance, emphasizing the role of algorithms such as the banker's algorithm and...
-
1. 2. 3. Suppose a consumer has a utility function U(x, y) = x0.5y0.5 and faces prices of Px = 4 and Py = 2. The consumer's income is $100. Find the optimal bundle of goods that maximizes the...
-
Use Boolean theorems to derive the Canonical POS expression of: BC + B(AD + AD')
-
Suppose the index goes to 18 percent in year 5. What is the effective cost of the unrestricted ARM?
-
In regards to delivering IT value, why is it so important for the business and its IT department to join efforts?
-
There are many tools available to assist organizations in implementing service management processes. Tools are needed to capture performance, usage metrics from the various platforms, and to...
-
Mention potential areas a company policy related to End-user Computing groups should cover.
-
Read the Ideas in Action section about Melinda Gates. Respond to the following questions based on Gatess experiences and your own experiences: A. What are some of the negative consequences of trying...
-
For each of the following items, respond with one or two paragraphs. A. Discuss how you can establish and build credibility before, during, and after your presentations. B. Describe the importance of...
-
Think about a recent presentation you attended that you found effective. In three to five paragraphs, describe why it was effective. Include the following aspects in your analysis, referring to...
Study smarter with the SolutionInn App