Question: If a project is on schedule its schedule performance index (SPI) should have what relation to 1.0? Group of answer choices SPI = 1.0 SPI
If a project is on schedule its schedule performance index (SPI) should have what relation to 1.0? Group of answer choices SPI = 1.0 SPI > 1.0 SPI < 1.0