If a project with a duration of 1 year had an actual cost of $30,000, a planned
Fantastic news! We've Found the answer you've been seeking!
Question:
If a project with a duration of 1 year had an actual cost of $30,000, a planned cost of $50,000, and a value completed of $25,000 at the end of 6 months, what are the CPI, SPI and CSI for the project?