Question: If a project's earned value is $18,000 and its planned value is $6,000, what would its schedule performance index suggest? a It will cost $24,000

If a project's earned value is $18,000 and its planned value is $6,000, what would its schedule performance index suggest? a It will cost $24,000 to complete the schedule. b It will cost $12,000 to complete the schedule. c The project is behind schedule. d The project is ahead of schedule. e Leave blank for now. I'll submit my answer later