Question: If a project's net present value is zero, the internal rate of return is: less than the discount rate. equal to the discount rate. greater
If a project's net present value is zero, the internal rate of return is:
less than the discount rate.
equal to the discount rate.
greater than the discount rate.
cannot be determined without more information.
None of the answer choices is correct.