Question: If a project's net present value is zero, the internal rate of return is: less than the discount rate. equal to the discount rate. greater

If a project's net present value is zero, the internal rate of return is:

less than the discount rate.

equal to the discount rate.

greater than the discount rate.

cannot be determined without more information.

None of the answer choices is correct.